Dianna boasts pioneering and writing a one of a kind multimillion dollar revenue generating program that allows construction of all budget sizes be permitted in one day by the District of Columbia. She interviewed and staffed the program and it is still in existence.
Construction Management and Project Management. Budget $46,255,617
Challenges
1. Design build
2. Technical client
3. Political Issues
4. Delicate mediums
5. Tight schedule
Construction Management and Project Management. Budget $8,000,000
Challenges
1. Design build
2. Tight schedule
3. Legal Issues
4. Political Issues
GC: Gilbane
Construction-Principal Construction Management and Project Management. Budget $17,525,059
Challenges
6. Design build
7. Tight schedule
8. Soft ground Scheduling
9. Near Surface Structures
10. Deep Shafts
11. Ground Improvement
GC: Gilbane
Construction—Permitting and Construction Management for 85,000 gross sq. ft. Budget $45,500,000
Challenges
Intersection and Georgia Ave
Tight Schedule
GC: Gilbane Construction—Permitting and Construction Management for 310,000 gross sq. ft. law school
facility which includes 245,000 gross sq. ft. of new construction combined with a 65,000 gross sq. ft. renovation
of the existing Capital Hall and Chapel
Challenges
1. Construction over a two level below grade parking structure
2. Support infrastructure located on the parking levels including primary electrical service rooms,
mechanical systems equipment including domestic water and fire suppression equipment
rooms, locker rooms and facilities offices
GC: Gilbane
Construction—Permitting and Construction Management for 42,350 sq. ft.
Challenges
1. Hazardous Materials Removal
2. Site clearing around existing structures
GC: Four Points LLC sub: Turner
Construction—Permitting and Project Management
GC: In-house—Permitting Management
Chevy Chase Village zoning code update; Chevy Chase, MD
GC: In-house—Senior Project Management
Anacostia River walk recreation design and
project management.
- Marine requirements
- Joint basing of Bolling & Anacostia for Economic Development
Coordination of streetcar project
Raze and Demolition building plans for 60 condos, 100 townhomes, and 27 single family homes and all phases of construction permitting for a $146 MM mixed-use project (tenant– UNCF)
Design-build, project management
Tax exemption status, historic preservation